First build in the history; nothing to compare against.
examples/showcase.nowline
nowline v1
roadmap showcase "Nowline Showcase" start:2026-01-05 scale:1m author:"Nowline"
anchor kickoff date:2026-01-05
swimlane engineering "Engineering"
item design "Design spec" duration:2w after:kickoff status:done
parallel after:design
group build "Build"
item api "API surface" duration:3w status:in-progress remaining:1w
item ui "Web client" duration:3w status:in-progress remaining:2w
item integrate "Integration tests" duration:2w
item ship "Ship" duration:1w after:integrate
swimlane marketing "Marketing"
item brief "Launch brief" duration:1w after:kickoff status:done
item assets "Launch assets" duration:3w after:brief
item announce "Announcement" duration:1w after:ship
milestone launch "Launch" after:[ship, announce]